Seven moves. Five artifacts. One plan. Part A carries Steps 1 to 4: set the boundary of the work, break it down, soft resource it, and turn it into a defensible labor budget. The plan carries forward to Planning Studio 2 in Part B, where you sequence it, schedule it, staff it, and draw the S-curve.
Oakhaven Public Safety Campus · GRC-26-0142 · Design Development · Oct 17, 2026 to Jan 15, 2027 · Grace phase fee $280,000A project plan is one argument, made five times, at increasing resolution: here is the work, here is what it costs, here is when it happens, here is how the fee gets earned, and here is the line we manage to.
The Planning Studio runs across both planning modules, and it runs in seven steps. Steps 1 to 4 sit here in Part A, where you Establish Clarity about the work and its cost. Steps 5 to 7 sit in Part B, where the same plan flows into the schedule, the labor demand, the Earned Value Plan, and the S-curve. Every decision you commit here rides along.
Step 1 · Set the scope boundary
The SD package was approved and the DD notice to proceed is in hand. Below are the 19 work packages your team has floated for this phase.
Step 1 · Set the scope boundary
Decide what work belongs in this phase before you plan anything else. Work let into scope by mistake still gets budgeted, scheduled, and paid for out of the $280,000 phase fee.
This is the first of seven steps. Every step that follows, the WBS, the budget, the schedule, only covers the work you place inside this boundary.
A scored boundary decision. You need 19 out of 19 correct before Step 2 unlocks.
19 work package cards. Each card has two buttons: In DD scope and Not this phase.
In DD scope or Not this phase on every card.Check my boundary to score your answers.Check my boundary again.Show the answers to see the correct boundary.Step 3 · Soft resource the work
Step 3 · Soft resource the work
Assign a role, not yet a person, to the work. Answer at the lowest level that can still do the work right. The DD fee is $280,000. Grace's target profit is 20%, so your cost budget, everything you may spend on labor, is $224,000.
Step 3 turns the locked WBS (Step 2) into hours by role. Step 4, right below, reads those same hours as money.
A table of hours per role, and a live dashboard of total hours, labor cost, planned margin, and average team loading.
A role-by-role hours table covering the Oakhaven team's eight roles, pre-populated with the hours filed in the Design Development phase of the Project Budget Spreadsheet. The dashboard updates as you type. A Suggest a starting mix button offers a benchmarked default at any time, to compare against.
Suggest a starting mix at any time to see a benchmarked default and compare it to the pre-populated plan.Step 4 · Build the budget
Step 4 · Build the budget
Read the hours you entered in Step 3 as money, and check whether the plan holds margin. The dashboard above and the flags below are one budget seen two ways: what the plan costs, and what margin survives it.
Step 4 closes Part A. Once locked, the WBS and the budget both carry forward into Planning Studio 2.
A validated budget with pass or fail flags (for example, a flag if labor cost exceeds the $224,000 cost budget, or if a required role has zero hours), and, once available, a comparison to the plan Grace actually filed in BST.
The flags list below the budget table, and a Compare to the plan Grace filed in BST button.
Compare to the plan Grace filed in BST to check your numbers against the filed plan.Lock the budget → Step 5: sequence and schedule once your margin is at or above the 15% firm floor and no red flags remain. This locks both Step 3 and Step 4.