Grace Design Studios · Module 5 of 12 · Part A

Quick Reference · The Budget Builder

Planning Process · Part A · Companion Reference Guide

The five questionsA worked budget exampleSoft-resource guide
1

Questions 1 to 3

From scope to budget

Planning answers five questions in order. This module is the first three, turning scope into work, roles, and a price. The last two, When and Who, are Part B. These three questions are how you Establish Clarity about the work and what it costs, and they are Steps 1 through 4 of the seven step plan.

Question 1

What is the work?

Decompose scope into a WBS: phase → deliverable → work package → task.

Tool · WBS hierarchy
Question 2

Which roles?

Soft-resource each task to the lowest level that can do it right.

Tool · Soft-resource guide
Question 3

How much?

Assign hours, price by role, roll up against the fee.

Tool · The budget builder
Question 4

When?

Sequence the work: Logic-Based Planning, critical path, float.

→ Part B
Question 5

Who?

Hard-schedule the role demand onto real people.

→ Part B
Planning Studio · Where this guide gets used

This guide is the reference. Planning Studio 1 is the practice. Everything below runs live on Oakhaven’s Design Development phase: the hierarchy, the builder logic, and the rates. There, draw the scope boundary, build the 9-deliverable WBS, then staff $224,000 of labor across the eight-role roster and commit it. Keep this page open while working the Studio. Open Planning Studio 1 →

2

Decompose the scope

The WBS hierarchy

A Work Breakdown Structure decomposes the project in four levels, each more concrete than the last. Decompose down to tasks small enough to assign and price.

1

Major Project Phase

A billing phase. SD · Design Development · CD

2

Project Deliverable

A physical output. Floor Plans · Elevations · RCPs · Outline Specs

3

Work Package

A major component of a deliverable. Partition layout · Egress overlay · MEP coordination

4

Task

Assigned to one role. Draft partition types · Run egress calc · Tag wall ratings

Decomposing real DD scope language, the quick version of the Module Overview walkthrough:

Contractual scope clauseDeliverables → sample tasks
“…prepare Design Development Documents to fix and describe the architectural character: plans, elevations, sections.”Floor Plans → draft partition types, run egress calc, dimension to grid. Elevations → material & opening layout. Sections → cut key building sections.
“…coordinate the structural, mechanical, electrical and plumbing systems within the documents.”Structural set → reconcile arch grid with framing. MEP set → locate mech rooms & chases, coordinate dispatch power & clearances.
“…together with outline specifications and material selections.”Outline Specs → draft CSI section outline. Materials → select assemblies & finishes, assemble DD board.
Planning Studio · The live version

The Oakhaven DD WBS inside the Studio is this hierarchy made real: phase 3.0 → 9 deliverables → 14 work packages → 40 assignable tasks, verbatim from the project’s filed WBS. Step 1 makes you earn it. Five packages from other phases are shuffled into the deck, and each one let in spends fee the phase does not have.

3

A worked example

Rates and a worked budget

One real Oakhaven Design Development package: six tasks, staffed and priced against a $100,000 phase fee, from the 2026 Grace Hourly Rate Schedule. Read it the same way you will read your own. This is Questions 1 to 3, made tangible.

Task (WBS)Role (soft-resource)HoursCostFlag
Dispatch-floor plans & RCPArchitect · $155120$18,600✓
Exterior elevations & sectionsArchitect · $15570$10,850✓
Structural coordinationSenior Architect · $17090$15,300●
MEP integration & redlinesProject Manager · $150110$16,500✓
Code & egress reviewSenior Architect · $17030$5,100●
QA review & DD issuePrincipal · $31040$12,400▲

Flag the rate as you read it: ▲ $310+ is the top of the rate card, reserved for judgment work. ● $170–$309 is senior, so confirm the task needs it. ✓ under $170 is the efficient floor for production work.

Total hours
460
Planned cost
$78,750
Fee
$100,000
Profit / margin
$21,250 · 21.3%
Planned cost as a share of fee79%
Healthy plan at 21.3% margin. Built bottom-up from tasks, roles, and hours. This is a budget you can defend and measure execution against.

Rates are the 2026 Grace Hourly Rate Schedule (effective 01/01/2026). Profit shown is fee minus planned labor cost, before consultants and reimbursables. Build your own plan, role by role, in Planning Studio 1.

Planning Studio · The builder with a spine

Step 4 of the Studio is this budget builder wired to consequences: live margin against the $280,000 fee, a hard 15% commit floor, and flags for the classic failures. Those flags catch QC unbudgeted, PM effort too thin to control the phase, and Principal hours crowding the rate mix. Committed numbers carry into Part B and, at the end of Studio 2, onto the BST screens exactly as they would be loaded on a real project. Build the budget →

4

Match the role to the work

Soft-resource guide

“Lowest competent level” is the rule. Match the nature of the work to the floor at which it is still done responsibly. That floor is neither the cheapest body nor a Principal doing production work.

Nature of the workTypical floor roleDo not use a…Why
Production drafting, plans, RCPs, schedulesArchitect / Design ProfessionalPrincipal in ChargeRepeatable technical output. A senior rate buys judgment the task does not need, and it erodes margin without improving the drawing.
Discipline & consultant coordinationSenior Architect / Project ManagerDesign ProfessionalResolving conflicts across disciplines and holding consultants to the schedule takes standing a Design Professional does not carry.
Schedule, fee, scope & client decisionsProject ManagerDesign ProfessionalContractual and financial exposure. These are PM-of-record decisions; delegating them below the PM breaks the chain of accountability for the fee.
Code, egress & life-safety judgmentSenior ArchitectDesign ProfessionalLife-safety interpretation calls for licensed judgment and experience with AHJ review, not production-level execution.
QA / QC review & sealing the setQC Peer Reviewer / Principal in ChargeArchitect (unsealed)Sealing requires the license, and the review requires independence: the reviewer cannot be the person who produced the work.
BIM standards, model setup & auditingBIM ManagerDesign ProfessionalA specialized technical skill. Model integrity problems surface late and expensively if a specialist does not own the standards from the start.
Document formatting, proofing, assemblyAdministrative, not on this rosterProject ManagerNo technical judgment required. Routing it to a design or PM role spends billable technical capacity on non-technical work.

The Oakhaven roster is eight roles: Principal in Charge, Project Manager, Senior Architect, Architect, Design Professional 1, Design Professional 2, BIM Manager, QC Peer Reviewer. Any role outside that list is priced from the firm rate card and has to be added to the plan deliberately.