Your work plan lays out the workload peaks and valleys and also helps visualize where the most critical project hand offs will happen. The Project Manager's next task is to align the communication cadence and style to the needs of the project through effective Communication Planning.
Written lesson · the complete walkthrough · companion to the Quick ReferenceModule Home › Module Overview
On the Oakhaven Public Safety Campus the team meets every Tuesday at nine, and it has since kickoff. Attendance is good, the agenda is stable, and the notes go out the same afternoon.
Everyone arrives and reports out on what they are working on and reports that they are "on track." The team leaves the meeting feeling accomplished and confident.
The scheduled meeting works exactly as designed. It is consistent and it takes the full hour, no matter what is happening on the project that week.
There's one problem: the meeting does not adapt to the changing needs of the work. Communication Planning solves that by mapping the communication style and duration to the needs of the work by syncing the communication approach to the project plan.
You built a work plan in Module 5. It names the major work packages, assigns them to owners, estimates the hours for various staff, and creates logical linkages between tasks to ensure the Critical Path does not slip. In Module 7, you will lead two kickoff meetings where you share the plan and communicate expectations.
Module 6 is the part in between. It creates the communication rhythm and rules that will tie the plan to the actual work and keep the team moving in the same direction during the project.
Almost nothing in a communication plan is new. The places where the team needs working sessions, reviews, and decision dates are already in your work plan. Your job is to design the communication and the project's interactions according to where those items sit, put them on a calendar, and ensure the intensity of communication matches the intensity of work.
From memory. What does your work plan hold that a calendar doesn't, and what does that thing tell you about when the project has to talk?
Dependency links. Every task in your work plan carries what must exist before it can start, and the links that cross a discipline are your coordination milestones. A calendar carries dates and no logic at all. That's why you can write one before you've planned the work, and why you can't do that with a communication plan.
The majority of Project Managers start each project with a recurring calendar invite. That recurring calendar sets one communication rate and holds it for the entire phase. On Oakhaven, that means your Design Development check in happens the same way in Week 2, when 4 people are working and nothing's been decided, and in Week 11, when 14 people are working and 3 disciplines are waiting on the same answer.
That fixed cadence has the potential to hurt the project twice.
Early, the cadence produces meetings with little to decide, and your team may learn the meeting is optional. Then when the workload peaks, the same cadence delivers a fraction of what the work needs, and by then nobody takes it seriously.
Communication planning is about syncing the communication demand of the project to the calendar, and realizing that a fixed communication style is not appropriate when work is dynamic.
Coordination your work plan required and your calendar never scheduled.
You can count it.
What's left is your debt for the phase. It's the number of major coordination items minus the number of coordination sessions to coordinate them.
It gets more expensive the longer it sits. A stale assumption caught in Week 8 costs you a small amount of rework. Caught in Week 14, it costs the rework, the consultant coordination to reissue, and whatever the schedule slip costs on top.
In recent years, the calendars of many Project Managers have become covered with meetings. It is a top complaint among AEC Project Managers and it contributes to feelings of stress and "I do not have enough time" that are widely reported in the field. The simplest first step for a Project Manager to create more time and space for themselves and better control their calendar is to become more intentional with how you schedule communication.
There are three main things that earn a slot on your calendar for a given project. These are not the only things, but these are a "Top 3" list.
| Trigger | Where you find it | What it earns |
|---|---|---|
| 1 · Work intensity | A phase boundary or a staffing increase in your work plan | A review of communication intensity to ensure it is right-sized to the work. |
| 2 · Coordination milestone | A dependency link between tasks held by different disciplines | A dedicated work session to resolve and document the issue. |
| 3 · Client decision point | Any task that can't start until your client chooses | A dedicated communication at the "request by" date for the decision and a future meeting to solidify the decision. |
In a typical phase, effort starts slow while decisions are being made, climbs once the big decisions lock, then eases off as the work moves into review. Coordination follows that curve as a leading indicator, because it's a function of how many people are working and how many handoffs sit between them.
A best practice is to separate the communication plan for a phase into three zones:
That's the shape of communication during the project. Magnitude is a separate question, and it comes from how many parties must talk to each other directly. Projects with many staff or many consultants will have more complicated communication networks than smaller, less busy projects.
Communication planning answers when to talk, and who has to talk to whom. The first is set by the calendar. The second sets how much of the calendar you need. When the party count is high, meetings may need to be longer. The longer the meeting, the more important the leadership of the PM to keep the communication successful.
A coordination milestone is any point where 2 or more disciplines have to trade information to keep the other party on track. Grace's coordination milestones are already in your work plan, inside the dependency links between tasks owned by different roles.
Finding them is mechanical and, with a high-quality plan, a relatively easy task. Find the places in the plan where any task has a predecessor that sits with another discipline, then put a working session at the handoff.
Working sessions are dedicated communications that aim to solve a specific problem, make a specific discipline-to-discipline decision, or finalize a specific component of the project. They are collaborative in nature, but still led by the Project Manager.
A client decision point is any moment your client must make a choice or decision before the work continues. Strong Project Managers identify the date for each decision and then count backwards from that date to determine when the decision must be requested. To determine when you need to ask for decisions, the Project Manager must understand the client's decision latency.
Decision latency measures how long it takes a client to make a major decision. This timeframe can be procedural, such as when a board meets. It can be personal preference, meaning some people make decisions faster than others. The Project Manager should gather data about the client's decision process early so that they can plan the request by dates for major decisions.
Take the Oakhaven dispatch system selection. The console room package can't start until the vendor is selected, because the equipment sets the room dimensions, the power requirements and the clearances. That package starts in Week 11. Oakhaven's a new client, so the Project Manager's latency estimation came from Grace's experience on comparable municipal decisions, and it came out at 3 weeks. The request had to go out in Week 8, with options and a recommendation.
If it goes out in week 9 or week 10, we've put the project in a difficult position. The Communication Planning process identifies these key dates and then plans communication activities into the calendar to ensure they are met.
Start from your Module 5 work plan. Everything you need is in it.
Step 6 gives you the page you present at kickoff. Module 7 covers how you introduce it and how you hold the team to it.
Put the page away. Name the 3 triggers, state the request by calculation, and name the 5 conversations with the output each one owes you.
The triggers are work intensity, a coordination milestone and a client decision point. Request by date = decide by date − client decision latency. Giving direction produces a task somebody can start Monday. Monitoring progress produces a percent complete read against the plan. Evaluating work produces one of 3 verdicts. Client communication produces a decision made or a decision scheduled with a date. Maintaining updates produces a record anyone can read without asking.
Next. The Quick Reference is your job aid. Print it and keep it beside you while you build the plan and run it.
Additional Materials holds the deeper content, including how communication debt gets counted and priced.
Tell us what landed this week. It takes about 3 minutes, and it shapes what we cover in the live session.