Grace Design Studios · Module 8 of 12
Job aid. The Friday routine, the four line review, the 7 field PM Plan, and the gap route. Print it and keep it beside you on Friday.
Module Home › Quick Reference
Friday decides Monday. Before you close the week, compare the week that ended to the plan, then build the week that starts. The comparison runs first, because what it finds becomes next week's priorities.
Progress is a comparison. Module 5 already wrote the four lines you compare against, so most weeks the review is a lookup and it takes minutes.
Every gap and every Friday answer becomes a PM Plan entry with 7 fields and a time on the calendar. Anything with no time on it is still an intention.
Seven moves. These are the ones that decide whether the week holds.
Seven signals. Each one is visible on a Friday, and each one costs more the longer it sits.
Ask them in this order, about the project, before you build anything. Each one tends to surface a different horizon.
| Ask | What it usually surfaces |
|---|---|
| What matters most? | Next week. The item that cannot slip without costing something. |
| Who needs something from me? | Next week. People are already waiting, and they are quiet about it. |
| What should already be underway? | The next several weeks. Long lead items, consultant deliverables, client decisions. |
| What am I avoiding? | The next milestone. The unresolved thing that gets expensive on its own schedule. |
Scan all 3 every Friday. Most weeks the first fills and the other 2 hold 1 or 2 items each.
| Horizon | The question it asks | Oakhaven, week 8 |
|---|---|---|
| Next week | What has to move, and who is waiting on me? | Elevations has to start Monday. The hours conversation cannot slip. |
| The next several weeks | What needs attention now because it has lead time? | Karen Whitfield's City Council briefing, 3 weeks out. |
| The next milestone | What has to be true before the project gets there? | The owner furnished dispatch system is still unresolved. |
One entry per Priority. All 7, or the plan is not finished.
| Field | The question | Oakhaven example | The test |
|---|---|---|---|
| Priority | What matters next? | Elevations has not started and sits on the critical path. | Could somebody else read it and know what it is? |
| PM Action | What do I personally need to do? | Get elevations under way and settle the hours in the same conversation. | Is it an action you take, not one you hope for? |
| People | Who needs to be involved? | The architect of record and the elevations lead. | Are these names, not disciplines? |
| Date and time | When will I address it? | Monday 8:30, 30 minutes. | Is it on the calendar, with a clock time? |
| Communication | Who needs to know, and through what channel? | Marcus Webb, email, Monday afternoon. | Is the channel one they actually read? |
| Project Control | Where will the outcome live? | The schedule. Resequenced dates go in the same day. | Decision Log, risk tracking, or schedule? |
| Closure | How will I know it is closed? | Elevations is under way and week 11 has not moved. | Is it something you can see, not something you assume? |
The plan wrote these at the start of the phase. Every week you put actual beside planned and name the difference.
| Line | The question the plan answers | Where it lives | What must be true to prove it |
|---|---|---|---|
| Work | Which packages should be done, and which active? | Work Breakdown Structure and schedule | The finished package exists as a document and you have seen it. |
| Time | Where should the work sit against the milestone and the critical path? | Schedule | Every active package sits where the schedule says. |
| Effort | Whose hours should have gone in, and how many? | Budget and resource plan | Hours spent match what the budget planned for work completed. |
| Fee earned | How much fee should the completed work have earned? | The effort curve | Fee earned by completed work tracks the curve. |
Five documents, all of them built before this phase started. The review is a lookup when they are current.
| Open this | Read this out of it |
|---|---|
| The schedule | Planned dates for every active package, the critical path, and the next milestone. |
| The Work Breakdown Structure | Which packages should be closed by now, and which should be running. |
| The budget and resource plan | Planned hours for the work completed, by package and by person. |
| The effort curve | Fee the completed work should have earned by the end of this week. |
| Last week's PM Plan | What moved, what did not, and what changed. Start the review here. |
If one of these takes more than a minute to read, that is a planning problem, and it will cost you again next Friday.
Three branches, and every outcome lands in the project controls.
| What the outcome is | Where it lands |
|---|---|
| A date moved, or work resequenced | The schedule |
| A decision made, by you or by the client | The Decision Log |
| A new exposure, or one that grew | The risk tracking |
| A commitment the client made or received | The client commitment record |
Same gap, same project, 4 weeks apart. Early discovery buys options, and the options expire.
| Found | The elevations package is late | What you can still do |
|---|---|---|
| Week 7 | Costs a Monday conversation with the team. | Resequence the work, add a person, or take the client a recommendation. |
| Week 11 | Costs another person, or overtime, or both. | Absorb it, or tell the client after the fact. |