Grace Design Studios · Module 9 of 12
Job aid. The 8 steps of the monthly review, the numbers and how to get them, the 3 states, the 4 recovery levers, billing and collections, the weekly check, and a BST Dashboard Explainer. Keep it open at the prebill.
Module Home › Quick Reference
Run the monthly review on every phase before the prebill. Steps 1 to 5 find where the phase is and how it will finish. Steps 6 to 8 bill, collect, judge the phase, and plan the next month.
Update the Estimated Hours before you read any other number. Percent complete, Revenue, the invoice and the forecast all come from them. Effort to date divided by the Budget Effort measures only money spent.
Name the state, then do its response this month. Off track goes to the PIC as a recommendation. At risk goes on next week’s PM Plan as a Priority.
Effort is cost. Your target effort is the Budget Effort less your profit goal. A $280,000 phase at a 20 percent goal has a target effort of $224,000.
Print the Monthly Review Field Resource (PDF) for the whole review on one sheet, front and back.
Seven actions. Do them in this order at each monthly review.
Seven warning signs. You can find each one on the PM dashboard or in the weekly check.
Seven habits that seem helpful but cause problems.
Each number, how you get it, and the Oakhaven DD value from the videos.
| Number | How you get it | Oakhaven DD |
|---|---|---|
| Budget Effort | The contract fee for the Task. Grace says fee. BST records it as Budget Effort. | $280,000 |
| Target effort | The Budget Effort less your profit goal. It has no column on the dashboard. | $224,000 |
| Effort | The burdened dollar value of the hours charged. The average direct labor rate times a uniform overhead ratio, so Effort is cost. | $112,000 to date |
| Estimated Hours | Hours to date plus hours to finish, person by person, from the team. | From the team |
| Estimated Effort | Estimated Hours × rate. The total effort the phase will use. Your working forecast. | $280,000 |
| EAC | The accounting value BST uses to recognize revenue. The Project Accountant updates it from Estimated Effort. | $224,000, 25 percent low |
| Percent complete | Effort to date ÷ Estimated Effort. | 40 percent |
| Revenue | Percent complete × Budget Effort. The Budget Effort earned to date. | $112,000 |
| Effort Remaining | Budget Effort minus Effort to date. The Budget Effort that is left. | $168,000 |
| Effort Performance Index | Revenue ÷ Effort. 1.0 is break even. The plan is 1.25 at a 20 percent goal. Add it as a column. | 1.00 |
| Invoice | Percent complete × Budget Effort, minus the total billed to date. | $28,000 |
Judge the phase before step 8. Each state has a test and a response.
| State | Test | Response |
|---|---|---|
| On track | Estimated Effort is at or below the target effort, and the work due is done. | Continue with the plan. |
| At risk | The forecast profit is below the plan, and at or above the margin floor in your Module 5 plan. Or the weekly check shows an early warning. | Work the recovery levers. A gap you can close goes on next week’s PM Plan as a Priority. |
| Off track | The forecast profit is below the margin floor, a milestone was missed, or Estimated Effort is above the Budget Effort. | Update the forecast and size the gap. Take a recommendation to the PIC with the situation, the options, your recommendation and the first action. |
Use them in this order. Each lever applies to a different cause.
| Lever | Use it when | Example from the module |
|---|---|---|
| 1 · Close the open decision | A client or internal decision holds up the work or causes redraws. | Pinewood DD. The board has not approved the finish palette. |
| 2 · Rework the resource plan | Senior staff do work that a lower cost role can do well. | Oakhaven DD elevations. Magnolia CD wall sections. |
| 3 · Re scope the remaining work | The remaining work does not fit the remaining Budget Effort after levers 1 and 2. | Agree the new scope with the PIC first. |
| 4 · Price the changes to the scope | Scope changes cause the problem. | Module 10 |
You control the time from earned work to invoice. Grace’s collections protocol is in the Module 3 AR Guide.
| When | Action | Who |
|---|---|---|
| Every month | Bill to percent complete. | Project Manager |
| Unbilled Days above 30 | Earned work waited more than one billing cycle. Bill it now. | Project Manager |
| Day 45 | Make the specific ask to the client. | Project Manager |
| Day 60 | Call the client, with the PIC aware. | Project Manager |
| After the invoice | Follow up with the client’s accounts payable team. | Accounting |
Run it yourself first, then take the gaps to the weekly project team meeting.
| Hours | Work | What it means |
|---|---|---|
| On plan | Done | The week went to plan. |
| On plan | Behind | Less progress per hour than the plan assumed. An early warning, so the phase is at risk. |
| Under plan | Behind | The staffing is short, or the work started late. |
Hours Remaining stays at zero when the team works to the schedule. Below zero, decide if the work needs more Estimated Hours or if future scheduled hours can come out. Make the change with the Project Accountant.
A recreation of the BST PM dashboard with Oakhaven DD selected. Choose a field, or click a column name or a panel title, to see what it shows, how to read it, and the step that uses it.