Grace Design Studios · Module 10 of 12
Job aid. The five steps, the Change Log, the agreement question, the four part conversation and the two path script. Keep it open at kickoff and on every call where a client asks for something extra.
Module Home › Quick Reference
Change management is a comparison against an expectation you set on day one. Steps one through four get built once, at kickoff and in the agreement. Step five runs every time the boundary moves.
Before you say any number, including “no charge,” ask one question. Does the agreement already include this?
On the call, the warmth comes first and the confirmation comes second. I would love to help you with that. Thank you for asking.
Seven actions. These are the ones that decide what a change costs you.
Seven signals. Each one shows up in a meeting or an email, and each one costs more the longer it sits.
Seven habits. Each one feels helpful in the moment.
One entry per request, opened the day it arrives. Every field, every time.
| Field | What you write | Oakhaven example |
|---|---|---|
| Date | The day the request arrived. | September 18, 2026 |
| Description | What was asked, in plain words. | Secure evidence storage room in the police wing. |
| Reason | Why the change is needed, and who raised it. | Owner request in a design review. Not in the program. |
| Estimated cost | Hours and fee, or $0. | $12,500 plus coordination. |
| Impact | What it changes in schedule, coordination and scope. | Security consultant added. Layout reworked. |
| Status | Approved, Declined, or Watched. | Approved September 28. Amendment 01, fee plus $12,500. |
| Status | Use it when |
|---|---|
| Approved | The work goes ahead, inside Basic Services or under a signed amendment. The Fire Marshal’s separation was Approved at $0. |
| Declined | The client or Grace decided not to do the work. Keep the entry. |
| Watched | Nobody has acted on it yet. Grace’s alternate roof assembly option was Watched. |
SD, DD, CD 30, CD 60 and CD 90. Put them on the schedule the client already sees.
Run the checks in this order on every request. Assemble the package before you bring a number to anyone.
| Check | Why it sits here |
|---|---|
| 1 · Schedule | A change against a fixed end date is the easiest to miss until it is expensive. |
| 2 · Coordination | An extra meeting or review cycle shows up on a timesheet and never on a drawing. |
| 3 · Scope | The agreement already writes it down. |
| Package item | The question it answers |
|---|---|
| Outside the agreement | What does the request add beyond the agreement? |
| Effect on work in progress | What does it change in work already under way? |
| Time estimate | How long, and does holding the schedule need more people? |
| Coordination added | Which meetings, reviews and consultants does it add? |
Four answers. The contract decides, whoever raised the request.
| Answer | The test | What you do |
|---|---|---|
| Basic Services | The agreement already includes the work. | Log it as Approved at $0, and do the work. |
| Additional service | The work falls outside the agreement. | Assemble the package, return the impact, offer the two paths. |
| Take it to the PIC | The contract is unclear rather than silent. | Say no number to the client until the PIC reads the clause. |
| Log and watch | Nobody has asked for the work yet. | Log it as Watched, and run the checks if the client says yes. |
Sort the request before the conversation starts.
| Size | The test | What you do |
|---|---|---|
| Small | It does not move a review period, and it does not add real coordination hours. | Log it, say it warmly, move ahead. “I would love to help with that, and it is small enough to note in our change tracker and move ahead.” |
| Large | It touches the schedule, the coordination or the scope. | Run the whole four part conversation, in order. |
A large change gets all four parts, always in this order.
| Part | What you do | Say it like this |
|---|---|---|
| Name it early | The moment you sense a request might touch the change rule. | “This might touch what we agreed on changes. Let me check before we go further.” |
| Acknowledge | Open with interest, before any confirmation. | “I would love to help you with that, thank you for asking. Let me confirm what it affects before we commit.” |
| Check | Run the three checks and assemble the package internally. | Nothing to the client yet. |
| Return | Give the impact in time first, then the fee. | “This is about a week of work across three disciplines…” |
| Choose | Offer both paths as equal, and let the client pick. | The two path script, below. |
Say it as written, and offer both paths as equals. Both are a yes to more work.
The scripted answers from Video 2. Keep the first words the same every time.
| Situation | Say this first | What you agree to |
|---|---|---|
| The client says “just start” | “I would love to get you moving on this right away. Let me confirm the impact before we release the team, and I will have an answer for you by tomorrow.” | Speed, with the check still in place. |
| It looks outside the agreement | “I would love to help you get there. That looks different from what the agreement currently includes, so let me check the agreement and confirm the impact before we tell you whether this needs an amendment.” | Help, and a check of the document. |
| A code official drives it | “This requirement changes the work, and we are glad to help you meet it. That does not automatically mean it is an additional service, so we need to compare it against the agreement and understand the impact first.” | Meeting the code. The contract decides who pays. |
| Your team found it first | To the team. “Don’t start yet. Show me where this sits against the current scope, and what changes if we do it.” | A same day log entry, before the hours are spent. |
A verbal yes shows intent, but it does not by itself authorize the work. The conversation is finished when every line below is done.