Module 10 taught you to compare every request against the agreement. Module 11 applies the same check to the drawings. Before a set goes out, the team must confirm it is ready. You are accountable for the process that confirms it.
Written lesson · the complete walkthrough · companion to the Quick ReferenceModule Home › Module Overview
You’re the Project Manager on Oakhaven. The QC Reviewer received the Construction Documents set yesterday, Thursday. Signing and sealing happens Friday.
The reviewer has one day to read the set. The team has no time left to pick up what the reviewer finds.
Whose problem is that?
The answer is in section 4. In short, the problem started weeks earlier, when nobody put the review on the phase plan.
Module 10 taught you to compare every request against the agreement. This module applies the same check to the drawings. Before the Architect of Record signs and seals the Oakhaven construction documents, you must be able to answer one question. What proves this set is ready?
Grace has a written process to answer it. Quality Assurance and Quality Control is a collaborative process. Specific people do specific tasks at set times, with set tools, and then the result is verified. Section 3 explains the process. Section 4 explains your role in it.
QA/QC uses the plan you already have. In Module 5 you built the phase plan. In Module 8 you compare the week against it every Friday. QA/QC adds the review dates to that plan, and then checks that each review happened.
From memory. What does every review on the Module 5 phase plan need? Then name the comparison Module 8 runs every Friday.
A real date and a named person. Module 8 compares what the plan says against what is true, on the four lines of work, time, effort and fee earned. Module 11 puts the QA Review and the Quality Review on the same plan, and checks them the same way.
A problem found during a design review is a simple correction. The same problem found after the set is issued costs more to fix. A problem found during construction becomes rework or a change order.
This is what it means to Protect Integrity on a project. The QA/QC process finds problems early, when they cost less and the team has more options. Grace’s lifecycle map states the rule.
That rule sets 2 conditions before the project moves to the next phase. The work meets the standard. And the right people know about and accept any item that is still open.
Grace has a written process and the tools to run it. The process still fails in 3 common ways.
You can find all 3 on the schedule or on the QC Form. You do not need to open a drawing.
Responsible means you do the work. Accountable means you answer for the outcome. Technical staff make the technical decisions, such as whether a detail meets code, whether a clash is acceptable at this milestone, or whether the set is ready to sign and seal. The discipline leads and the Architect of Record make these decisions. Your job is to make sure every step of the process happens on time, is complete, and is recorded.
Each role in section 3 is responsible for part of the work. The Project Manager is accountable for the whole process.
Grace’s QA/QC process has 4 parts. Specific roles do specific tasks at set times, with set tools. Then the result is verified.
Grace names 5 roles.
| Role | What they do |
|---|---|
| Design team | Checks its own drawings against the QA Prompts, and performs its own quality control review at the end of each phase. |
| Storyteller | An emerging designer who shadows you. Keeps the record, books the QC Reviewer on the dates you set, sends the QC Form with the checklists, and composes the A3. |
| QC Reviewer | Reviews the QC Form and performs the quality control review against the BIM Quality Control Checklist. At the end of Construction Documents, the reviewer comes from outside the project team and outside the office. You choose the reviewer. |
| Architect of Record | Reviews the QC Form, checks the drawings, and signs and seals them. |
| Storyteller Ambassador | Your office Ambassador onboards your Storyteller. Grace invites the Ambassador to the project. |
You are accountable for the process that connects these 5 roles. Each role depends on the dates you set.
Grace assigns the work by phase. Figure 2 shows the full sequence.
Two steps on the timeline matter most. In Pre Design, you and your Storyteller identify the project schedule with QA/QC dates for each phase. Through Schematic Design, Design Development and Construction Documents, you choose the QC Reviewer and set the review dates. Your Storyteller books the reviewer at least 3 weeks before the signing and sealing deadline, and puts those dates on your calendar and the reviewer’s.
Every other step depends on these 2.
Grace built every tool this process runs on.
| Tool | What it is |
|---|---|
| Milo | The project request, the QC forms, the QA/QC staff list, and the BlueBeam QC tools. |
| QA Prompts, BIM and Excel | The checklist the design team uses to check its own drawings. The team edits it for each project. |
| BIM Quality Control Checklist | What the QC Reviewer checks the set against. |
| Quality Control Form | The QA/QC record that travels with the set. |
| Centerline | The lifecycle information, the progress reports, and the QA/QC metrics. |
| A3 | The project story, composed by the Storyteller and reviewed by you at closeout. |
The Grace QA/QC Process page lists where each tool lives and who requests it.
The Quality Control Form carries the phase due dates, the reviewer names, and a row for each review at each phase. Here are the 4 review rows, in the form’s own labels.
| Row on the form | What it records |
|---|---|
| Design Review / Design Standards Review | The design standards review for the phase. |
| Building Code / Zoning Review | The building code and zoning review. |
| QA Reviews / Red-lines Back Checked | The design team’s own check against the QA Prompts, and whether the red lines were picked up and back checked. |
| QC Peer Review | The independent review by the QC Reviewer, also called the Quality Review. |
Below the grid sits the Design Team Report. Its Areas Under Development field lists the areas the design team wants the reviewer to look at for this milestone. Grace asks for the form at every phase, and on addenda, ASIs and early release packages.
The top of the form gives one instruction. Provide adequate time for review and red line pickup before the issue dates. Plan the time for red line pickup when you plan the review.
The result is verified in 3 places.
You’re accountable for the process, and for confirming it’s complete before work goes out. You do this in 4 steps in every phase: schedule, prepare, drive and verify. Each step starts at a specific point in the phase.
Schedule starts when you build the phase plan, the same process you followed in Module 5. Grace asks you for one thing in Pre Design. Identify the project schedule with QA/QC dates for each phase.
So every QA Review and Quality Review goes on the schedule with a real date and a named reviewer. Do not write TBD.
You choose the QC Reviewer for each phase and set the review dates. Your Storyteller books the reviewer on those dates, at least 3 weeks before the signing and sealing deadline, and puts them on your calendar and the reviewer’s. At the end of Construction Documents the reviewer comes from outside the project team and outside the office, so choose that reviewer early. If the project needs more than 3 weeks, decide that at the start of the phase.
You do. The Storyteller does not choose or assign the QC Reviewer. The review dates come from your phase plan, and the Storyteller books them. When a video says the Storyteller schedules the QC Reviewer, it means the Storyteller books the dates you set.
The form tells you what else to plan. It asks for adequate time for review and red line pickup before the issue dates. So the review, the pickup window and the back check go on the plan together.
These decisions are yours alone. You choose the QC Reviewer. You decide whether extra reviews are required, consultant reviews included. And you edit the QA Prompts with the design team, which sets the scope of the review and tells you how much time it needs.
This answers the question in section 1. A reviewer with one day cannot do a full review. The problem started at the beginning of the phase, when nobody put the review on the schedule. The Project Manager owns that problem. One date on the phase plan prevents it.
Prepare starts when a review date is on the calendar and the package hasn’t gone out. Before the QA Review, ask one question. Did every discipline check its own work against the prompts, or did some of them just say they did?
Confirm means you looked at the record yourself. Grace names the records to check. The design team reviews the BIM QA sheet prompts before the set gets printed for the end of phase review. Your Storyteller PDFs each sheet with the BIM QC Checklists and saves them to the project folder.
Then the QC Form goes to the QC Reviewer and the Architect of Record, with the checklists. Grace makes the Project Manager responsible for a complete form, so read it before it goes. Check 3 things.
A set sent to a reviewer the day before the deadline does not get a full review. Send it with the time the plan allows.
Drive starts when the review comments come back. The team picks up the red lines and back checks them. The QA Reviews / Red-lines Back Checked row on the form records this.
If that row is blank, nobody has confirmed that the corrections are in the drawings.
Some items cannot close before the phase ends. Record them in the Design Team Report on the QC Form, under Areas Under Development. Write an open item there, and the QC Reviewer and the Architect of Record both see it before the set goes out.
You don’t judge how serious a finding is. The QC Reviewer or the discipline lead does that. Your job is to make sure their decision, and the status of every correction, is recorded.
Design Development, the 60 percent milestone. The quality control review came back with 4 findings. Two are back checked and closed. Two are open.
One is an HVAC clash tied to the redundancy decision that has sat with Karen Whitfield, the client, since Module 9. The other is the generator pad against geotechnical bearing capacity.
It’s Wednesday. The set goes out Friday. The mechanical lead says, “We’re fine, we’ll pick that up next phase.”
Can Dana, the Project Manager, release it?
That’s a technical call, and Dana isn’t the one who makes it. What she can do is check the record, in 3 places.
The HVAC clash has a reason, a lead and a decision date. It goes on the form as an area under development, and the reviewer gets it with the set.
The generator pad has no answer yet, because structural and geotechnical haven’t agreed. Dana can’t resolve it, and the mechanical lead can’t either. So it goes to the discipline lead today, and Dana tells Karen before Friday which open items the set includes.
Practice. Read 3 QC Forms and decide what each one tells you.
Three Quality Control Forms, one at a time. Each is open at the Design Development column. Pick what the form tells you.
Form 1 of 3 · A phase about to close
The phase closes this week. Your Storyteller hands you the form before it goes to the QC Reviewer and the Architect of Record.
| On the form | This phase, DD |
|---|---|
| Phase Due Dates | Entered |
| QC Peer Reviewer 1 | Named |
| Design Review / Design Standards Review | Entered |
| Building Code / Zoning Review | Entered |
| QA Reviews / Red-lines Back Checked | Blank |
| QC Peer Review | Reviewer name and review date |
What the form tells youThe review happened, but nobody has confirmed that the corrections are in the drawings. The phase is not ready. Until that row is filled, nobody can say the phase is ready.
Look againThe QC Peer Review row shows that somebody independent looked at the set. The back check row answers whether the red lines were picked up, and it is empty.
Look againThe reviewer’s row is complete. The empty row is the design team’s pickup and back check. Ask the team whether the corrections reached the drawings.
Form 2 of 3 · Early in the phase
Design Development started 3 weeks ago. You open the form to check the plan for the end of the phase.
| On the form | This phase, DD |
|---|---|
| Phase Due Dates | Blank |
| QC Peer Reviewer 1 | Blank |
| Design Review / Design Standards Review | Blank |
| Building Code / Zoning Review | Blank |
| QA Reviews / Red-lines Back Checked | Blank |
| QC Peer Review | Blank |
What the form tells youThe Schedule step never happened. Fill in the phase due dates and name the QC Reviewer first. A blank due dates row and a blank reviewer box mean the review is not on anyone’s calendar. That is the first thing to fix.
Look againThe review rows do fill in later. The due dates and the reviewer belong to Pre Design, and without them nobody books the reviewer 3 weeks ahead.
Look againThat is a Prepare question. With no dates and no reviewer, there is nothing to prepare for yet. Start with Schedule.
Form 3 of 3 · The day before the set goes out
Every review row is filled. You know 2 items are still open, and the set goes out tomorrow.
| On the form | This phase, DD |
|---|---|
| Phase Due Dates | Entered |
| QC Peer Reviewer 1 | Named |
| Design Review / Design Standards Review | Entered |
| Building Code / Zoning Review | Entered |
| QA Reviews / Red-lines Back Checked | Entered |
| QC Peer Review | Entered |
| Design Team Report | |
| Areas Under Development | Blank |
What the form tells youThe QC Reviewer and the Architect of Record cannot see the 2 open items. Record them in Areas Under Development before the set goes out. The form looks complete, but it leaves out 2 open items. The Design Team Report is where Grace records open items for the QC Reviewer and the Architect of Record.
Look againThe rows are filled, but 2 items are still open. The form does not show them, so the QC Reviewer and the Architect of Record will not see them.
Look againThat is a technical call. The QC Reviewer or the discipline lead judges how serious a finding is. Your job is to make sure it is recorded.
What you read
Open the Quality Control Form on your own project this week and read it the same way.
The last step is sign and seal. The Architect of Record receives the QC report, reviews the form, checks the drawings, and then signs and seals.
If the set reaches the Architect of Record without a complete form, a step in the process was missed. Find the missed step and complete it. After the phase, the results are counted. Your Storyteller captures the metrics in Centerline and composes the A3, and you review it at closeout.
Name the 4 steps and what starts each one. Then name the 4 review rows on the Quality Control Form.
Schedule starts when you build the phase plan. Prepare starts when a review date is on the calendar and the package hasn’t gone out. Drive starts when the comments come back. Verify starts when a set is about to go out. The 4 rows are Design Review / Design Standards Review, Building Code / Zoning Review, QA Reviews / Red-lines Back Checked, and QC Peer Review.
Next. The Quick Reference is your job aid. Print it. The Grace QA/QC Process page carries Grace’s own wording for every step, with the source for each.
Then Module 12, Closeout and Debriefing. Items still open at the end of design often become issues during construction.
Sources for this page. Every step comes from a Grace document. QA/QC Implementation, 4 August 2026. QAQC Timeline, Project Manager, 9 September 2026. Storytellers Timeline. Grace Quality Control Form. QA Prompts v1.0.